- Fix with the specified pattern. Countersunk screws or nails at the system’s centres, heads sunk just below the face — never proud, never torn through the paper.
- Leave a 2–3 mm gap between boards. The taper is not a zero-gap system; the gap absorbs hygric movement.
- Fill the channel, then tape. Push cement-based joint compound into the recess, bed a 100 mm alkali-resistant tape down the centre, and scrape off the excess so the tape is just covered.
- Spot the fixings. Fill every screw head with the same compound; this is where rust bleed and telegraphing start if it is skipped.
- Two thin coats, then sand. Thin coats shrink less and sand flatter than one heavy fill.
Two mistakes account for most callbacks: using gypsum joint compound on a cement substrate, which loses adhesion and cracks, and over-filling the taper so the joint becomes a ridge.
Tapered vs square vs bevelled edge
| Tapered (TE) | Square (SE) | Bevelled | |
|---|---|---|---|
| Joint appearance | Flush, seamless | Visible line or shadow gap | Defined chamfer, decorative |
| Preparation before paint | Local jointing only | Full-surface skim or accept the line | None, the chamfer is the detail |
| Best use | Internal painted walls and ceilings | External cladding, dry-fix, floors | Feature walls, edge protection |
| Labour | Low | High, or zero if left exposed | Low |
| Stock | Often made to order | Standard | Standard |